July 31, 2015

Work Completed from 07/20/15 to 07/31/15:
  • Approximately 1,350 linear feet of 12-inch ductile iron water main and 10x6 dual-walled HDPE force main, in a common trench, on the SW side of Davis Ford Road to just east of Alford Valley Lane.
  • All work has required the use of flaggers to maintain traffic; delays have been minimal.
On the horizon for the next couple of weeks:
  • Install 12-inch ductile iron water main and 10x6 dual-walled HDPE force main, in a common trench, on the SW side of Davis Ford Road from Occoquan Oaks northwesterly for approximately 800 feet.
  • Install Fire Hydrants and valves according to the plans.
  • Flaggers will continue to manage traffic; you can expect to see continued delays along the work route for the next couple of weeks.
  • All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.
  • Daily inspection and maintenance of temporary asphalt patching.