Approximately 500 linear feet of 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road from Asdee Lane northward.
Installed permanent pavement restoration of Davis Ford Road in between the intersections of Prince William Parkway and Bacon Race Road.
All work has required the use of flaggers to maintain traffic; delays have been minimal.
On the horizon for the next couple of weeks:
Install 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road from Bacon Race Road northward.
Flaggers will continue to manage traffic; you can expect to see continued delays along the work route for the next couple of weeks.
All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.
Daily inspection and maintenance of temporary asphalt patching.
Follow Us
Latest Tweets
As we defrost from last night's snow, check out this handy graphic from @NoVARegion to help you do your part in kee… https://t.co/C52yrH9KaL —
1 hour 53 min ago
RT @fairfax_water: In our area, severe weather and other emergencies can happen at any time. Take steps now to store emergency water… https://t.co/Xh4a2fxgPT —
1 day 52 min ago
@pwcsa has seen a lot of changes since its inception 40 years ago, including the construction of the Raymond Spittl… https://t.co/RTmEZ2PAIu —
3 days 17 hours ago