October 13, 2015

Work Completed from 09/28/15 to 10/09/15:
  • Approximately 820 linear feet of 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road to just beyond the entrance to the Occoquan Forest Water Reclamation Facility (OFWRF).
  • All work has required the use of flaggers to maintain traffic; delays have been minimal.
On the horizon for the next couple of weeks:
  • Install 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road for approximately 1,000 feet northward approaching Occoquan Forest Drive.
  • Excavation of bore pits on either side of Davis Ford Road at the intersection with Occoquan Forest Drive / River Forest Drive.
  • Install a pressure reducing valve vault on the north side of the OFWRF entrance.
  • Install the jack and bore of the water and force mains under Davis Ford Road at Occoquan Forest Drive / River Forest Drive intersection.
  • Install Fire Hydrants and valves according to the plans.
  • Work schedule is 9:00 AM to 4:00 PM Monday - Friday.
  • Flaggers will continue to manage traffic. Delays are expected along the work route for the next couple of weeks.
  • All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.
  • Daily inspection and maintenance of temporary asphalt patching.