Approximately 820 linear feet of 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road to just beyond the entrance to the Occoquan Forest Water Reclamation Facility (OFWRF).
All work has required the use of flaggers to maintain traffic; delays have been minimal.
On the horizon for the next couple of weeks:
Install 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road for approximately 1,000 feet northward approaching Occoquan Forest Drive.
Excavation of bore pits on either side of Davis Ford Road at the intersection with Occoquan Forest Drive / River Forest Drive.
Install a pressure reducing valve vault on the north side of the OFWRF entrance.
Install the jack and bore of the water and force mains under Davis Ford Road at Occoquan Forest Drive / River Forest Drive intersection.
Install Fire Hydrants and valves according to the plans.
Work schedule is 9:00 AM to 4:00 PM Monday - Friday.
Flaggers will continue to manage traffic. Delays are expected along the work route for the next couple of weeks.
All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.
Daily inspection and maintenance of temporary asphalt patching.
Follow Us
Latest Tweets
This week is Chesapeake #BayAwarenessWeek! Use the River Runner app to follow the journey of a raindrop through the… https://t.co/0QGLVgmRZP —
3 hours 32 min ago
We're hiring for a variety of roles and have placed our ads at the Woodbridge and Rippon VRE stations. Continue you… https://t.co/RDLppK3xDg —
1 day 4 hours ago
There's still time to sign up for the e-Bill Sweepstakes! 20 lucky customers who sign up for electronic billing or… https://t.co/ZgxbiIlv3s —
2 days 3 hours ago