Heritage Hunt Sewage Pump Station Replacement and Force Main

Webpage Updated March 6, 2023
Project Manager
David R. Scott, PhD, PMP
Project Description
Replacement of the existing Heritage Hunt Sewage Pumping Station (SPS) to increase pumping capacity from 3.6 Million Gallons Per Day (MGD) to 7.81 MGD. The new, higher-capacity SPS will be capable of serving the anticipated build-out of residential and commercial developments in and around the Heritage Hunt community. A new 24-inch Force Main will be constructed from the SPS to a location at the corner of Heathcote Boulevard and Route 29.
Project Status
The design, permitting and advertisement for bids occurred from July 2020 through January 2022. The bid opening for the construction contract was on February 15, 2022. The Board of Directors approved the award of the construction contract on April 14, 2022. Construction began in August 2022 and the estimated final completion is August 2024.