March 5, 2015

Progress on the Project was impacted due to freezing weather and snow. Please see updates since February 19, 2015 and projections through March 13th. All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.

Updates since February 19, 2015:
  • Approximately 600 linear feet of 6-inch ductile iron sewer main on the west side of Davis Ford Road just north of Prince William Parkway.
  • Flaggers have assisted in managing traffic; you can expect to see this for the next couple of weeks.
  • Delays have been minimal as we avoid the morning and evening commute.
On the horizon for the next couple of weeks:
  • Continued installation of the 6-inch sewer main on the west side of Davis Ford Rd northward to Asdee Lane.
  • Installation of silt fencing along Asdee Lane and a small section of 12-inch ductile iron water main (south side of Asdee) near the intersection with Great Bridge Drive.
  • Begin work on an 8-inch water line along the north end of Occoquan Forest Drive and at two (2) other small sections near River Run and Twin River Drives.