April 27, 2015

Work Completed from 04/10/15 to 04/24/15:
  • Approximately 1,300 linear feet of 8-inch PVC water main on the west side of Occoquan Forest Drive continuing southward.
  • Approximately 690 linear feet of 12-inch ductile iron water main on the south side of Asdee Lane out into the intersection with Davis Ford Road.
  • Approximately 350 linear feet of 6-inch ductile iron force main on the west side of Davis Ford Road, just north of Prince William Parkway.
  • All work has required the use of flaggers to maintain traffic; delays have been minimal.
On the horizon for the next couple of weeks:
  • Continued installation of the 8-inch PVC water main on the west side of Occoquan Forest Drive towards Davis Ford Road.
  • Install 12-inch ductile iron water main and 10x6 dual walled HDPE force main, in a common trench, on the SW side of Davis Ford Road from Asdee Lane northward.
  • Flaggers will continue to manage traffic; you can expect to see continued delays along the work route for the next couple of weeks.
  • Daily inspection and maintenance of temporary asphalt patching.
  • All planned work is subject to change and is contingent upon the appropriate weather for underground utility installation.
  • Contractor to provide schedule to permanently restore Davis Ford Road, for areas south of Asdee Lane that currently have a temporary patch.